Legal Review

Government COVID-19 Restrictions and the Application of Force Majeure Clauses: Lessons from a UK Case

On June 24, 2022, in the case of N KD Maritime Limited v. Bart Maritime (No 2) Inc (Shagang Giant) [2022] EWHC 1615 (Comm), the Commercial Tribunal of the High Court of England and Wales (hereinafter referred to as the Court) ruled on the "force majeure clause" stipulated in the contract...

The English text below is a convenience translation. The complete original Chinese text follows it.

(Hint from the UK case)

On June 24, 2022, in the case of N KD Maritime Limited v. Bart Maritime (No 2) Inc (Shagang Giant) [2022] EWHC 1615 (Comm), the Commercial Tribunal of the High Court of England and Wales (hereinafter referred to as the Court) interpreted the "force majeure clause" stipulated in the contract, finding that the government restrictive measures taken in response to the COVID-19 pandemic did not constitute force majeure. The buyer's act of terminating the contract by invoking the force majeure clause is invalid. Therefore, the court supported the seller's claim, ruling that the buyer's termination of the contract constituted a breach of contract and had no right to demand a refund of the down payment already made.

1. Factual Background of the Case

To scrap all its large ore vessel "S HAGANG GIANT," built in 1993, Bart signed a contract (Memorandum of Agreement) with NKD on March 5, 2020, to sell the vessel to NKD, agreeing to transport the vessel from Singapore to Alang, India, where it would be recovered by the shipbreaking yard in Alang.

This case mainly involves the following two contract terms:

Clause 2

(a) Delivery Location

The Vessel shall be delivered and taken over safely afloat at outer anchorage Alang, West Coast India, which shall be the “Delivery Location”.

I f, on the Vessel’s arrival, the Delivery Location is inaccessible for any reason whatsoever including but not limited to port congestion, the Vessel shall be delivered and taken over by the Buyer as near thereto as she may safely get at a safe and accessible berth or at anchorage which shall be designated by the Buyer, always provided that such berth or anchorage shall be subject to the approval of the Seller which shall not be unreasonably withheld. If the Buyer fails to nominate such place within 24 (twenty four) hours of arrival, the place at which it is customary for vessel (sic) to wait shall constitute the Delivery Location. The delivery of the Vessel according to this paragraph shall constitute full performance of the Seller’s obligations and all other terms and conditions of this Agreement shall apply as if delivery had taken place.

Upon delivery, the Vessel shall be recycled at a Ship Recycling Facility …

( c) Delivery Notice s

The Seller and/or their agents will give 5, 3 and 1 (five, three and one) days approximate notice of arrival at the Delivery Location, in accordance with the terms and conditions of this Agreement.

I f for reasons beyond the Seller’s control the Vessel has not arrived at the Delivery Location on or before 1700 hours local time on the Cancelling Date and the Seller and the Buyer have failed, having acted in good faith, to reach mutual agreement on an extension to the Cancelling Date then the Buyer shall have the right to cancel this Agreement provided written or telegraphic notice of such cancellation is given to the Seller by the Buyer within 48 (forty eight) hours after notice of such delay is given by the Seller to the Buyer. …

Clause 10 Force Majeure

Should the Seller be unable to transfer title of the Vessel or should the Buyer be unable to accept transfer of the Vessel both in accordance with this contract due to outbreak of war between the nominated country of delivery and any other country, wreck, actual constructive or compromised total loss of the Vessel, restraint of governments, princes, rulers or people of any nation or the United Nations, act of God, then either the Buyer or the Seller may terminate this Agreement upon written or telegraphic notice from one party to the other without any liability upon either party and the Initial Payment referred to in Clause 1.1. hereof shall be released to the Buyer.

The suspension or termination of the activities of the Ship Recycling Facility shall not constitute a force majeure event under this Agreement and the Buyer agrees to pay for and take delivery of the Vessel in accordance with the terms and conditions of this Agreement and after delivery, the Buyer shall be at liberty to ballast the Vessel to another Ship Recycling Facility … for Recycling.

After signing the above agreement, NKD paid Bart Company 30% of the total contract price as a down payment (US$4,264,723.13). However, on March 21, 2020, the vessel was prohibited from entering the Khambat Bay Vessel Traffic Management Center area (hereinafter referred to as the VTS area), so it had to anchor outside the VTS area. Starting March 24, in response to the COVID-19 pandemic, the Indian government implemented restrictions including lockdowns, which suspended ship recycling activities at the Arang shipbreaking plant. On April 14, the Indian Prime Minister announced that the lockdown measures would last until May 3. During this period, the vessel involved was never able to enter the VTS area.

On April 14, NKD invoked Article 10 of the contract to terminate the contract, arguing that the blockade measures imposed by the Indian government starting March 25 were force majeure events that had persisted, preventing Bart from transferring ship ownership under the contract and NKD being unable to receive ship ownership under the contract. On April 15, Bart Company replied, stating that there was no force majeure event and NKD had no right to terminate the contract on this basis, considering NKD's request to terminate the contract as a refusal to perform. On that day, NKD invoked Clause 2(c) of the contract and issued another notice of contract termination.

On May 6, Bart sold the vessel to another company (Best Oasis Ltd.), and delivered the vessel to the latter on May 26.

2. Dispute between both parties

NKD Company argued: The Indian government's pandemic lockdown measures prevented Bart from transferring ship ownership under the contract. Under Article 10 of the contract, NKD had the right to terminate the contract and demand a refund of the down payment.

Bart Company argued: Clause 10 of the contract does not apply to this case. Bart Company did not encounter circumstances where the ship could not be transferred, and transferring ship ownership does not require delivery of the vessel; Even if delivering a vessel is a necessary condition for transferring ship ownership, Bart has not been unable to deliver vessels due to force majeure events (i.e., government restrictions). Therefore, NKD Company's notice of contract termination constitutes a refusal to perform, and Bart Company has the right to retain the down payment and claim losses and expenses incurred due to its breach.

NKD and Bart both filed lawsuits against each other, and on June 5, 2020, the court ordered a consolidated trial.

3. Court determination

The court held that the fundamental focus of the dispute was whether NKD Company's notice of contract termination was legal and valid. If the answer is yes, NKD has the right to demand a refund of the down payment; If the answer is no, NKD constitutes default, and Bart has the right to retain the down payment and receive compensation for losses exceeding it.

To address the above focus, the court began by analyzing and discussing the following specific aspects based on Article 10 of the force majeure clause on which NKD Company was based on the termination of the contract:

(1) Does the provision in this clause "transfer of ship ownership according to contract agreements" necessarily require delivery of the vessel?

(2) Does "delivery under contract" require delivery at a specific location? If so, did Bart fail to deliver at that location?

(3) Are these deliveries not caused by government restrictions?

(4) Was Bart Company's failure to fulfill the contract due to NKD's lack of cooperation?

Taking into account the relevant facts, the court held that:

(1) In the context of the contract, the "transfer of ship ownership" stipulated in Article 10 does not necessarily require delivery of the vessel. Therefore, in the absence of an impossibility of transferring ownership of the vessel, delivering the vessel solely under the agreed delivery terms is insufficient to support terminating the contract by invoking Article 10 (force majeure clause).

(2) Although the vessel involved was unable to reach the original delivery location due to failure to obtain permission to enter the relevant area, it had tried to approach the aforementioned location as close as possible. In other words, the vessel's inability to reach the originally agreed delivery location is due to the objective inaccessibility of the area at that location, while the actual anchorage is the "usual waiting area" for ships that have not obtained permission to enter the Alang outer anchorage during the same period. In this situation, NKD Company has failed to specify an alternative delivery location within the agreed timeframe. Accordingly, Clause 2(a) of the contract shall apply, and the vessel's anchorage outside the VTS area constitutes the place of delivery, and upon arrival at that location, the seller shall be deemed to have fulfilled its obligations to deliver the vessel. Accordingly, NKD Company claimed that the force majeure event did not hinder contract performance, and therefore it had no right to invoke the force majeure clause in Article 10 to terminate the contract.

(3) The vessel in question had not obtained permission to enter the Alang outer anchorage until April 14 (the contract termination date was April 15) because Gujarat Pollution Control Board (GPCB) personnel were instructed to fully collect and handle medical waste related to the COVID-19 pandemic. Moreover, even if the vessel entered the outer anchorage, the agency was effectively unable to conduct a written review or board inspection. Such circumstances are sufficient to constitute a "restraint of governments," but the key question is whether these restrictions mean Bart "cannot" transfer ownership of the vessel. The court held that the "cannot" here is clearly distinguished from the "obstruction" or "delay" used in general terms, nor can it be deemed "impossible" solely because the contract cannot be performed by the termination date; the key is whether the possible limitation period materially harms the commercial risk. After considering the nature of the contract and all relevant factors, the judge held that the delay until April 14 (which was reasonably foreseeable at the time of signing) did not constitute a "no" of performance under Article 10, and these delays did not materially harm commercial risk. If the contract is not terminated, the vessel is expected to obtain permission to enter the VTS area around May 1.

(4) The evidence is insufficient to support Bart's claim that the vessel's failure to obtain permits was due to NKD Company's failure to promptly seek local coordination, and that NKD Company subsequently took actions to obstruct the vessel's entry into the Alangwai anchorage.

Based on the above analysis, the court ultimately determined that NKD Company had no right to terminate the contract on April 14, 2020, and that the notice of termination constituted a breach of contract as stipulated in Article 8 of the contract and constituted a refusal to perform. Therefore, Bart Company is entitled to corresponding compensation.

Original language

Complete original Chinese text

The complete Chinese original migrated from the previous website and checked for completeness follows.

 

 

2022624日,在NKD Maritime Limited v. Bart Maritime (No 2) Inc (Shagang Giant) [2022]EWHC 1615 (Comm)一案中,英格兰及威尔士高等法院商事法庭(以下简称法院)通过对合同约定的“不可抗力条款”进行释义,认定该案中为应对新冠疫情而采取的政府限制措施不构成不可抗力,买方援引不可抗力条款终止合同的行为无效。因此,法院支持了卖方的诉请,判定买方终止合同的行为构成违约,无权要求退还已付首付款。

 

一、 案件事实背景

 

Bart公司为将其所有的建造于1993年的“SHAGANG GIANT”号大型矿砂船予以报废,于202035日与NKD公司签订了一份合同(Memorandum of Agreement,将该船售予NKD公司,约定将船舶从新加坡运至印度阿朗(Alang),由Alang的拆船厂对船舶进行回收。

 

本案主要涉及以下两个合同条款:

Clause 2

(a) Delivery Location

The Vessel shall be delivered and taken over safely afloat at outer anchorage Alang, West Coast India, which shall be the “Delivery Location”.

 

If, on the Vessel’s arrival, the Delivery Location is inaccessible for any reason whatsoever including but not limited to port congestion, the Vessel shall be delivered and taken over by the Buyer as near thereto as she may safely get at a safe and accessible berth or at anchorage which shall be designated by the Buyer, always provided that such berth or anchorage shall be subject to the approval of the Seller which shall not be unreasonably withheld. If the Buyer fails to nominate such place within 24 (twenty four) hours of arrival, the place at which it is customary for vessel (sic) to wait shall constitute the Delivery Location. The delivery of the Vessel according to this paragraph shall constitute full performance of the Seller’s obligations and all other terms and conditions of this Agreement shall apply as if delivery had taken place.

 

Upon delivery, the Vessel shall be recycled at a Ship Recycling Facility …

 

(c) Delivery Notices

The Seller and/or their agents will give 5, 3 and 1 (five, three and one) days approximate notice of arrival at the Delivery Location, in accordance with the terms and conditions of this Agreement.

If for reasons beyond the Seller’s control the Vessel has not arrived at the Delivery Location on or before 1700 hours local time on the Cancelling Date and the Seller and the Buyer have failed, having acted in good faith, to reach mutual agreement on an extension to the Cancelling Date then the Buyer shall have the right to cancel this Agreement provided written or telegraphic notice of such cancellation is given to the Seller by the Buyer within 48 (forty eight) hours after notice of such delay is given by the Seller to the Buyer. …

 

Clause 10  Force Majeure

Should the Seller be unable to transfer title of the Vessel or should the Buyer be unable to accept transfer of the Vessel both in accordance with this contract due to outbreak of war between the nominated country of delivery and any other country, wreck, actual constructive or compromised total loss of the Vessel, restraint of governments, princes, rulers or people of any nation or the United Nations, act of God, then either the Buyer or the Seller may terminate this Agreement upon written or telegraphic notice from one party to the other without any liability upon either party and the Initial Payment referred to in Clause 1.1. hereof shall be released to the Buyer.

 

The suspension or termination of the activities of the Ship Recycling Facility shall not constitute a force majeure event under this Agreement and the Buyer agrees to pay for and take delivery of the Vessel in accordance with the terms and conditions of this Agreement and after delivery, the Buyer shall be at liberty to ballast the Vessel to another Ship Recycling Facility … for Recycling.  

 

上述协议签订后,NKD公司向Bart公司支付了合同总价的30%作为首付款(US$4,264,723.13)。然而,2020321日船舶被禁止进入Khambat湾船舶交通管理中心区域(以下简称VTS 区域),因此只得在VTS区域之外抛锚。自324日开始,为应对新冠疫情(Covid-19),印度政府采取了包括封锁令在内的限制措施,据此,阿朗的拆船厂船舶回收活动暂停。414日,印度首相宣布有关封锁措施将持续到53日。期间,涉案船舶始终未能进入VTS区域。

 

414日,NKD公司援引合同第10条提出终止合同,认为印度政府于325日开始采取的封锁措施为不可抗力事件且一直持续,致使Bart公司不能依据合同转让船舶所有权,NKD公司不能依据合同接收船舶所有权。415日,Bart公司回复,认为不存在不可抗力事件,NKD公司无权据此解除合同,并将NKD公司提出终止合同的行为视为拒绝履约。当日,NKD公司援引合同第2 (c)条再次发出解除合同的通知。

 

56日,Bart公司转而将船舶售予另一家公司(Best Oasis Ltd.),并于526日向后者交付了船舶。

 

二、 双方争议

 

NKD公司主张:印度政府的防疫封锁措施阻碍了Bart公司依据合同转让船舶所有权,根据合同第10条不可抗力条款,NKD公司有权终止合同,并要求Bart公司退还已付首付款。

 

Bart公司主张:合同第10条不适用于本案,Bart公司没有出现无法转让船舶的情况,转让船舶所有权并不要求交付船舶;退一步讲,即使交付船舶系转让船舶所有权中的必要条件,Bart公司也没有因为不可抗力事件(即政府限制措施)而无法交付船舶。因此,NKD公司终止合同的通知系拒绝履约行为,Bart公司有权保留已付首付款并主张其违约而遭受的损失和费用。

 

NKD公司以及Bart公司均向对方提起了诉讼,法院于202065日下令合并审理。

 

三、 法院认定

 

法院认为,双方争议的根本焦点是NKD公司终止合同的通知是否合法有效。如果答案为是,则NKD有权要求返还首付款;如答案为否,则NKD构成违约,Bart公司有权保留首付款并就超出首付款的损失获得补偿。

 

为解决上述焦点,法院从NKD公司终止合同所依据的第10条不可抗力条款本身入手,分别就以下几个具体方面进行分析讨论:

1)该条款中约定的“依据合同约定转让船舶所有权”是否必然要求交付船舶?

2)“依据合同交付”是否要求在特定地点交付,如是,Bart公司是否未能在该地点交付?

3)该等交付不能是否系因政府限制措施而导致?

4Bart公司未能履行合同是否系因NKD公司欠缺合作而导致?

 

结合相关事实,法院认为:

1)结合合同上下文,双方在第10条中约定的“转让船舶所有权”并不必然要求交付船舶。因此,在没有出现不能转让船舶所有权的情况下,仅凭依据约定的交付条款交付船舶,不足以支持援引合同第10条(不可抗力条款)终止合同。


2)涉案船舶虽因未能获得许可进入相关区域而无法抵达合同原定交付地点,但已尽可能地接近前述地点。换句话说,船舶无法抵达合同原定交付地点系因该地点所在区域客观上不可进入,而船舶的实际锚泊地为同期未获得进入阿朗外锚地许可的船舶的“惯常等待地”。在此情况下,NKD公司一直未能在约定时间内指定替代交付地点。据此,合同第2a)条应予适用,船舶在VTS区域外的锚泊之地构成交付地,其抵达该地时即视为卖方已完成其交付船舶的相关义务。据此,NKD公司主张的不可抗力事件没有阻碍合同履行,因此其无权援引第10条不可抗力条款终止合同。


3)涉案船舶直至414日(合同约定解约日为415日)仍未能获得许可进入阿朗外锚地的原因是古吉拉特邦污染控制委员会(GPCB)人员被指令全力收集和处理与新冠疫情相关的医疗废物,而且,即使假设船舶进入了外锚地,该机构事实上也无法进行书面材料审查,更无法登轮检验。该等情况足以构成“政府限制”(restraint of governments),但关键问题是该等限制是否导致Bart公司“不能”转让船舶所有权。法院认为,此处的“不能”显著区别于一般条款中使用的“阻碍”或“延误”,也不能仅凭至解约日不能履行的状态就认为“不能”,关键是可能的限制期限是否实质损害了商业冒险。综合考量合同性质和各相关因素后,法官认为,直至414日的延误(某种程度上系双方签约时可合理预料到的情况)对Bart公司履约的影响不构成第10条规定的履约“不能”,这些延误没有实质损害商业冒险。假如合同没有被终止,船舶实际上是有望在51日左右获得进入VTS区域的许可的。


4)证据不足以支持Bart公司关于涉案船舶未能获得许可系因NKD公司未能及时争取地方协调导致,以及NKD公司后续采取了阻碍船舶进入阿朗外锚地的相关行为的主张。

 

基于上述分析,法院最终认定:NKD公司无权在2020414日终止合同,其终止合同的通知系合同第8条规定的违约行为,且构成拒绝履约。因此,Bart公司有权获得相应赔偿。

 

四、 评论

 

1. 为报废回收旧船而签署的船舶买卖合同区别于一般的船舶买卖合同,市场上往往没有国际通行文本,合同双方通常根据实际情况定制条款,因此,产生纠纷时,对合同用语的理解和解释尤为关键。本案中,法院即从理性务实的角度对有关合同用语进行分析和解释,尤其是针对合同条款里“Delivery Location”的理解与适用以及上下文中对“transfer of title”与“delivery of vessel”使用上的区别进行分析和推断,具有一定的指导意义。

 

2. 在全球新冠疫情这个特殊背景下,大部分国家或城市都曾或多或少地采取过与防疫相关的限制措施,即使该等措施对履行合同产生一定影响,但是否可以成功援引不可抗力条款终止合同,仍需要审慎考量。从本案来看,即使认定不可抗力事件(政府限制措施)客观存在,但该等影响是否最终导致履行不能,从维护合同稳定性的角度出发,法院一般都会适用较为严格的审查标准。仅凭相关限制措施在某个时间段短暂地阻碍或延误了合同的履行尚不足以支持认定合同“履行不能”,还应当综合涉案合同性质和各相关因素进行考量。

 

This English convenience translation is provided alongside the complete Chinese original, which prevails. Neither version constitutes legal advice on any specific matter.